Multiple Choice
The amount of delay within a task that will not delay the overall project is known as a
A) total slack.
B) estimated effort.
C) opportunity cost.
D) free slack.
E) both total slack and free slack.
Correct Answer:

Verified
Correct Answer:
Verified