Multiple Choice
Which of the following is true about hammock activities?
A) They are used to identify the use of fixed resources or costs over a segment of a project.
B) They are a combination of Start to Start and Start to Finish lags.
C) They are activities in which the costs are not subject to change.
D) They are an alternative description for the critical path.
E) They are highly sensitive.
Correct Answer:

Verified