Multiple Choice
___________ reflects the likelihood the original critical path(s) will change once the project is initiated.
A) Near-critical path
B) Sensitiveness
C) Sensitivity
D) Reactivity
E) Acuteness
Correct Answer:

Verified
Correct Answer:
Verified