After the Total Slack for Each Activity Is Identified, the Project

Question 26

Multiple Choice

After the total slack for each activity is identified, the project manager can more easily identify the


A) earned value.
B) critical path.
C) earliest start date.
D) total project slack.
E) total budget.

Correct Answer: