menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 3
  4. Exam
    Exam 6: Developing a Project Schedule
  5. Question
    An Activity Has a Duration of 10 Days
Solved

An Activity Has a Duration of 10 Days

Question 22

Question 22

Multiple Choice

An activity has a duration of 10 days. Its early start is 5 and its late start is 8. This activity has _____ days of total slack.


A) 1
B) 2
C) 3
D) 4
E) 5

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q18: _ slack is the amount of time

Q19: Consider the following table of activities A

Q20: Consider the following table of activities A

Q21: _ reflects the likelihood the original critical

Q23: In the network computation process what is

Q24: A(n) _ activity is frequently used to

Q25: Consider the following table of activities A

Q26: After the total slack for each activity

Q27: A project manager is building a project

Q90: Consider the following table of activities A

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines