Multiple Choice
An activity has a duration of 10 days. Its early start is 5 and its late start is 8. This activity has _____ days of total slack.
A) 1
B) 2
C) 3
D) 4
E) 5
Correct Answer:

Verified
Correct Answer:
Verified