Multiple Choice
A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,
A) the project will currently finish under budget, assuming the project continues to perform in this way.
B) the project will currently finish over budget, assuming the project continues to perform in this way.
C) the project will currently finish on budget, assuming the project continues to perform in this way.
D) the project will currently finish behind schedule, assuming the project continues to perform in this way.
E) there is insufficient information to draw conclusions.
Correct Answer:

Verified
Correct Answer:
Verified
Q69: The PCIC index measures the project percent
Q70: The _ index measures the project percent
Q71: Identify and describe two methods for tracking
Q72: For a more complex project, statistical analysis
Q73: When someone familiar with each task estimates
Q75: The cost variance for a project is
Q76: Given an EAC of $10,000 and a
Q77: What is scope creep and how does
Q78: The ratio that measures the amount of
Q79: Causes for scope creep can include<br>A) newly