When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the
A) 0 / 100 percent rule.
B) task complete rule.
C) degree complete rule.
D) work complete rule.
E) percent complete rule.