Multiple Choice
The first step in the project control process for measuring and evaluating project performance is to
A) set a baseline plan.
B) determine the project objectives.
C) determine the project deliverables.
D) analyze the project budget.
E) review the project priority matrix.
Correct Answer:

Verified
Correct Answer:
Verified