Multiple Choice
Which of the following methods will measure the cost efficiency of the work accomplished to date?
A) SV / CV
B) EV / PV
C) EV / AC
D) AC / SV
E) AC / CV
Correct Answer:

Verified
Correct Answer:
Verified