Multiple Choice
The third step in the project control process for measuring and evaluating project performance is to
A) review the baseline plan with top management.
B) analyze inputs to the control system.
C) compare the plan against actual performance.
D) measure both progress and performance.
E) review spending with team members.
Correct Answer:

Verified
Correct Answer:
Verified