Multiple Choice
A tool used to monitor past project schedule performance and current performance, and to estimate future schedule trends is a simple line chart known as a
A) Gantt chart.
B) network diagram.
C) PERT chart.
D) milestone chart.
E) project control chart.
Correct Answer: