A Project Can Have a Negative Schedule Variance and Still

Question 94

Multiple Choice

A project can have a negative schedule variance and still be ahead of schedule when


A) all budget targets have been achieved.
B) earned value exceeds planned value.
C) progress on the critical path is faster than non-critical path tasks.
D) actual cost exceeds earned value.
E) None of these alternatives is correct.

Correct Answer: