A Program Financial Accountant Learns That a Project Is Currently

Question 66

Multiple Choice

A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the


A) EV.
B) BAC.
C) SV.
D) SPI.
E) CPI.