Multiple Choice
A negative cost variance combined with a negative schedule variance is an indicator of
A) actual cost exceeding earned value.
B) planned value exceeding earned value.
C) budget over-runs.
D) behind schedule.
E) All of these alternatives are correct.
Correct Answer:

Verified
Correct Answer:
Verified