Multiple Choice
Which of the following is not a benefit of Earned Value Management?
A) Measures accomplishments against plan and deliverables.
B) Provides a method for tracking directly to a problem work package and organization unit responsible.
C) Enables the project manager to ascertain problem paths within the project network and when the critical path is underperforming.
D) Alerts all stakeholders to early identification of problems and allows for quick, proactive corrective action.
E) Provides for accountability over individual portions of the overall budget for each organization unit.
Correct Answer:

Verified
Correct Answer:
Verified
Q63: Progress and performance can be measured quantitatively
Q64: A negative cost variance combined with a
Q65: A project manager would be glad to
Q66: A program financial accountant learns that a
Q67: Which of the following is not one
Q69: The PCIC index measures the project percent
Q70: The _ index measures the project percent
Q71: Identify and describe two methods for tracking
Q72: For a more complex project, statistical analysis
Q73: When someone familiar with each task estimates