Question 41
True/False
The concept of earned value (EV) is particularly applicable to Agile projects.
Question 42
True/False
One way of linking planning and control is to monitor project progress on a Gantt chart.
Question 43
True/False
Physical asset control is concerned with the accounting system and the use of funds for the project.
Question 44
True/False
With Agile approaches, project scope is assumed to be variable as change is a welcome opportunity to incorporate new information and customer feedback to further enhance the value proposition of the product being developed.
Question 45
True/False
An important use of data analysis is to identify who to properly blame for poor project performance.
Question 46
Multiple Choice
The cost/spending variance is calculated as…
Question 47
True/False
Only senior scrum team members participate in the sprint review in order to keep the evaluation on track.
Question 48
Multiple Choice
Paulina, a fashion designer, has a new project that requires her to make five dresses in seven days. A sum of $2,000 is allotted to her to fund the entire project. In three days, she completes one-third of the work and spends $1,2Calculate the cost performance index from the given scenario.
Question 49
Multiple Choice
The most common source of changes to a project based on the natural tendency of the client and project team members to improve the project's output is called…
Question 50
True/False
Earned value is a measure for overall project progress in terms of performance, budget and schedule.
Question 51
Multiple Choice
David, an architect, is in charge of executing a housing project. He appoints Charles to collect, record, and report all the necessary information to David and other relevant stakeholders. In this scenario, Charles will be engaged in _____ the project.
Question 52
True/False
The most important use of data gathered from monitoring is learning from mistakes.
Question 53
True/False
The purpose of control is to ensure that all interested parties have the information they need.
Question 54
True/False
Control systems that make use of all five components of project control are called cybernetic control systems.
Question 55
Multiple Choice
_____ reports are primarily intended for special decisions or unexpected situations in which affected team members and outside managers need to be made aware of a change, and the change itself needs to be documented.