Multiple Choice
The most common source of changes to a project based on the natural tendency of the client and project team members to improve the project's output is called…
A) scope creep
B) projectitis
C) multitasking
D) dynamic scoping
E) unfreezing
Correct Answer:

Verified
Correct Answer:
Verified