Multiple Choice
William, a project manager, is trying to figure out how many hours his team can work in a period of three months. After accounting for weekends, he notes that each member of the team can work for five 8-hour days per week. After consulting his calendar, he realizes that there are three public holidays in the next three months and two employees have each requested two separate weeks off. His team consists of 15 people. Given this information, William can allocate approximately _____ of work to his team.
A) 7,200 hours
B) 6,120 hours
C) 7,600 hours
D) 6,680 hours
E) 5,500 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q13: If resources were not scarce, the resource
Q14: Arthur, a project manager, has multiple projects
Q15: The following describes which priority rule: With
Q16: The task duration with standard-practice resource usage
Q17: Lauren, a project manager, has a workload
Q20: The following describes which priority rule: This
Q21: What is fast-tracking a project?
Q22: One limitation of Microsoft Project is that
Q23: Crashing non-critical activities will influence project duration.
Q76: Resource loading refers to the amounts of