Solved

Lauren, a Project Manager, Has a Workload of 24,000 Hours

Question 17

Multiple Choice

Lauren, a project manager, has a workload of 24,000 hours that needs to be completed in 30 weeks. She has a team of 20 people who work five 8-hour days per week. She notices that in the 30-week period, there are five holidays and 5 members have each requested 10 days off. Given this information, Lauren is _____ short of completing her workload.


A) 1,200 hours
B) 2,500 hours
C) 2,000 hours
D) 1,500 hours
E) 3,800 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions