Multiple Choice
Lauren, a project manager, has a workload of 24,000 hours that needs to be completed in 30 weeks. She has a team of 20 people who work five 8-hour days per week. She notices that in the 30-week period, there are five holidays and 5 members have each requested 10 days off. Given this information, Lauren is _____ short of completing her workload.
A) 1,200 hours
B) 2,500 hours
C) 2,000 hours
D) 1,500 hours
E) 3,800 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Victoria, a project manager, has undertaken a
Q13: If resources were not scarce, the resource
Q14: Arthur, a project manager, has multiple projects
Q15: The following describes which priority rule: With
Q16: The task duration with standard-practice resource usage
Q18: William, a project manager, is trying to
Q20: The following describes which priority rule: This
Q21: What is fast-tracking a project?
Q22: One limitation of Microsoft Project is that
Q76: Resource loading refers to the amounts of