Multiple Choice
The following describes which priority rule: With this rule, resources are made available so that activities start on their latest start times (LS) whenever possible without increasing the project's duration.
A) As soon as possible
B) As late as possible
C) Shortest task duration first
D) Minimum slack first
E) Most critical followers