Multiple Choice
Verita Nist, an automobile company, sought to improve the production time and quality of its products within a year. In the first month, the company installed five new assembling machines. This reduced the production time by 15 percent. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM) , this decrease in the production time of Verita Nist's products is an example of a(n) _____.
A) task
B) activity
C) critical path
D) event
E) throughput
Correct Answer:

Verified
Correct Answer:
Verified
Q25: Networks are usually drawn with a "Start"
Q26: We can find the probability by finding
Q27: Slack is calculated as?<br>A) LFT - EST<br>B)
Q28: Scrum employs a consensus-based approach to develop
Q29: The movement from left to right through
Q31: There is more than one way to
Q32: When conducting risk analysis on a project,
Q33: Consider a project network that begins with
Q34: Define the term critical path.
Q35: What is a merger and what problems