Multiple Choice
Consider a project network that begins with activity A and is followed by activity B. Activity A takes 6 days to finish. If the earliest start time for activity B is 6 days and the latest start time for it is 10 days, activity B has a slack of _____.
A) 16 days
B) 4 days
C) 10 days
D) 2 days
E) 12 days
Correct Answer:

Verified
Correct Answer:
Verified