Multiple Choice
Scrum employs a consensus-based approach to develop estimates for the effort required to complete each product requirement listed in the product backlog. This consensus-based approach is called what?
A) Poker
B) Simulation
C) Statistical analysis
D) Bottle spinning
E) Estimation pokey
Correct Answer:

Verified