Multiple Choice
A project consists of the following four activities with activity times in days: Table 9.2
-Using Table 9.2, the earliest start (ES) time for activity B is
A) 5 days.
B) 6 days.
C) 11 days.
D) 14 days.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q2: A project consists of the following four
Q3: Which of the following statements is generally
Q6: The subjective estimate of the activity time
Q10: The following table of probabilistic time estimates
Q11: PERT stands for program enterprise and resource
Q11: Develop and analyze a probabilistic activity time
Q18: A project consists of the following activities:<br>
Q19: Why have projects taken on a more
Q36: Activities that are not on a project's
Q64: A _ breaks down a project into