Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the earliest finish time for activity C is
A) 5.00 weeks.
B) 8.17 weeks.
C) 9.50 weeks.
D) 12.67 weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: A project consists of the following four
Q6: The subjective estimate of the activity time
Q11: Develop and analyze a probabilistic activity time
Q12: A project consists of the following four
Q13: The following table of probabilistic time estimates
Q15: The following table of probabilistic time estimates
Q18: A project consists of the following activities:<br>
Q36: Activities that are not on a project's
Q51: Asian cultures tend to embrace project management's
Q64: A _ breaks down a project into