Solved

The Following Table of Probabilistic Time Estimates (In Weeks) and Activity

Question 10

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
The following table of probabilistic time estimates (in weeks)  and activity predecessors are provided for a project. Table 9.3   -Using Table 9.3, the earliest finish time for activity C is A)  5.00 weeks. B)  8.17 weeks. C)  9.50 weeks. D)  12.67 weeks.
-Using Table 9.3, the earliest finish time for activity C is


A) 5.00 weeks.
B) 8.17 weeks.
C) 9.50 weeks.
D) 12.67 weeks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions