Solved

The Following Table of Probabilistic Time Estimates (In Weeks) and Activity

Question 39

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
The following table of probabilistic time estimates (in weeks)  and activity predecessors are provided for a project. Table 9.3   -Using Table 9.3, the critical path for the project consists of activities A)  A-B-C-D-E. B)  A-B-C-E. C)  A-B-D-E. D)  A-B-C-D.
-Using Table 9.3, the critical path for the project consists of activities


A) A-B-C-D-E.
B) A-B-C-E.
C) A-B-D-E.
D) A-B-C-D.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions