Multiple Choice
In general,the latest finish time for an activity is equal to
A) latest finish time minus the activity time estimate.
B) the minimum of the latest start times for the activities that immediately follow.
C) the maximum of the latest start times for the activities that immediately follow.
D) the average of the latest start times for the activities that immediately follow.
Correct Answer:

Verified
Correct Answer:
Verified