Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the variance of the project's total completion time is
A) 5.472.
B) 5.222.
C) 4.872.
D) 3.752.
Correct Answer:

Verified
Correct Answer:
Verified