menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Study Set 1
  4. Exam
    Exam 9: Project Management
  5. Question
    The Following Table of Probabilistic Time Estimates (In Weeks) and Activity
Solved

The Following Table of Probabilistic Time Estimates (In Weeks) and Activity

Question 15

Question 15

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
The following table of probabilistic time estimates (in weeks)  and activity predecessors are provided for a project. Table 9.3   -Using Table 9.3, the variance of the project's total completion time is A)  5.472. B)  5.222. C)  4.872. D)  3.752.
-Using Table 9.3, the variance of the project's total completion time is


A) 5.472.
B) 5.222.
C) 4.872.
D) 3.752.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q10: The following table of probabilistic time estimates

Q11: Develop and analyze a probabilistic activity time

Q12: A project consists of the following four

Q13: The following table of probabilistic time estimates

Q16: Discuss the key elements of project control

Q51: Asian cultures tend to embrace project management's

Q65: Issues of cultural diversity in project management

Q83: For an activity-on-node (AON)network,<br>A)arrows represent activities and

Q93: The estimated mean time for an activity

Q98: The key elements of project control includes

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines