The Following Table of Probabilistic Time Estimates (In Weeks) and Activity

Question 13

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
The following table of probabilistic time estimates (in weeks)  and activity predecessors are provided for a project. Table 9.3   -Using Table 9.3, the probability that the project will take longer than 33 weeks to complete is approximately A)  0.19. B)  0.32. C)  0.68. D)  0.81.
-Using Table 9.3, the probability that the project will take longer than 33 weeks to complete is approximately


A) 0.19.
B) 0.32.
C) 0.68.
D) 0.81.