Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the probability that the project will take longer than 33 weeks to complete is approximately
A) 0.19.
B) 0.32.
C) 0.68.
D) 0.81.
Correct Answer: