A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product:
Without regard to projected demand, what is the minimum possible cycle time for this assembly line?
A) 0 seconds
B) 3 seconds
C) 9 seconds
D) 10 seconds
E) 28 seconds