True/False
The main function of dummy activities is to clarify relationships in network diagrams.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q91: Consider the portion of a project depicted
Q92: There are four activities on the critical
Q93: Given this information about activity 3-4: ES
Q94: Deterministic networks use three time estimates-shortest, most
Q95: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q97: Which of the following is not characteristic
Q98: A project is represented by the following
Q99: In which phase of the project life
Q100: The network diagram shows sequential relationships among
Q101: The standard deviation of the critical path