Multiple Choice
Consider the portion of a project depicted by this graph: What is the earliest finish time for activity 10-11 (far right-hand side) if the earliest start time of 8-10 (upper left-hand side) is 12 and the earliest start time of 9-10 (lower left-hand side) is 13?
A) 22
B) 23
C) 24
D) 25
E) 26
Correct Answer:

Verified
Correct Answer:
Verified