Solved

Activity 7-8 Is Directly Preceded by Two Activities-Activity 5-7 and Activity

Question 19

Multiple Choice

Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES time of seven. Activity 7-8 has an expected time of 10. The ES for activity 7-8 is


A) 11.
B) 14.
C) 21.
D) 24.
E) 25.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge