Multiple Choice
Consider the following work breakdown structure:
What is the estimated expected (mean) time for activity E?
A) 31 weeks
B) 38 weeks
C) 39 weeks
D) 40 weeks
E) 43 weeks
Correct Answer:

Verified
Correct Answer:
Verified