Multiple Choice
Consider the following work breakdown structure:
What is the estimated expected (mean) time for activity D?
A) 32 days
B) 41 days
C) 44 days
D) 42 days
E) 40 days
Correct Answer:

Verified
Correct Answer:
Verified