menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Statistics
  3. Study Set
    Operations Management Study Set 5
  4. Exam
    Exam 17: Project Management
  5. Question
    Consider the Following Work Breakdown Structure
Solved

Consider the Following Work Breakdown Structure

Question 9

Question 9

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated expected (mean) time for activity Y? A) 30 days B) 29 days C) 38 days D) 26 days E) 35 days
What is the estimated expected (mean) time for activity Y?


A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: If two consecutive activities have shared slack,

Q5: In the execution phase of a project's

Q6: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q7: Which of the following is not one

Q8: Which of the following are limitations of

Q10: In order to determine the probability of

Q11: A project is represented by the following

Q12: The path in a network with the

Q13: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q14: Concerning PERT and CPM<br>A)These are two different

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines