Multiple Choice
Consider the following work breakdown structure:
What is the estimated expected (mean) time for activity Y?
A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days
Correct Answer:

Verified
Correct Answer:
Verified
Q4: If two consecutive activities have shared slack,
Q5: In the execution phase of a project's
Q6: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q7: Which of the following is not one
Q8: Which of the following are limitations of
Q10: In order to determine the probability of
Q11: A project is represented by the following
Q12: The path in a network with the
Q13: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q14: Concerning PERT and CPM<br>A)These are two different