Multiple Choice
Consider the following work breakdown structure:
What is the estimated standard deviation in the time for activity Z?
A) 3 days
B) 2 days
C) 4 days
D) 8 days
E) 5 days
Correct Answer:

Verified
Correct Answer:
Verified
Q1: At which point does crashing of a
Q2: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q3: The latest starting time for an activity
Q4: If two consecutive activities have shared slack,
Q5: In the execution phase of a project's
Q7: Which of the following is not one
Q8: Which of the following are limitations of
Q9: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q10: In order to determine the probability of
Q11: A project is represented by the following