Multiple Choice
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:
Assume there must be one-to-one matching between consultants and projects. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?
A) 53 hours
B) 46 hours
C) 50 hours
D) 61 hours
E) 54 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Loading is the determination of which work
Q8: When orders exceed our capacity, priority rules
Q9: Which of the following is not a
Q10: Job X, which has a duration of
Q11: A scheduling technique used to achieve an
Q13: There are four resources and four jobs
Q14: The president of a consulting firm wants
Q15: The president of a consulting firm wants
Q16: High-volume jobs that often follow the same
Q17: As long as the bottleneck operations are