Multiple Choice
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:
Assume there must be one-to-one matching between consultants and projects. After the row and column reductions, what is the resulting entry in the new table for assigning Rick to project D?
A) 0 hours
B) 8 hours
C) 10 hours
D) 9 hours
E) 22 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q10: Job X, which has a duration of
Q11: A scheduling technique used to achieve an
Q12: The president of a consulting firm wants
Q13: There are four resources and four jobs
Q14: The president of a consulting firm wants
Q16: High-volume jobs that often follow the same
Q17: As long as the bottleneck operations are
Q18: Priority rules are widely used to sequence
Q19: Job X arrived at work center Q
Q20: The president of a consulting firm wants