Multiple Choice
The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
What is the makespan for the optimal schedule?
A) 24 hours
B) 25 hours
C) 26 hours
D) 28 hours
E) 50 hours
Correct Answer:

Verified
Correct Answer:
Verified