Multiple Choice
Which of the following options is the BEST definition of network planning?
A) Deciding the best way to set out processes in a factory
B) Breaking a project down into constituent processes to manage time efficiently
C) The design and implementation of an IT system
D) Optimising communications with business contacts to generate sales
Correct Answer:

Verified
Correct Answer:
Verified