Multiple Choice
What is a precedence table?
A) A tabular summary of the network
B) A table showing the events in order of importance
C) A table showing the activities in order of duration
D) A tabular summary of resources needed to complete a network
Correct Answer:

Verified
Correct Answer:
Verified