Consider the Following Network Diagram [Insert Network Diagram from Top

Question 6

Multiple Choice

Consider the following network diagram [insert network diagram from top of p555]. Which of the following statements is TRUE?


A) Activity F can start when Activity D is finished
B) Event 3 is complete when Activity B is complete
C) Activity E must wait for both Activity B and Activity C to finish
D) Activity B can start when half of Activity A is complete