Multiple Choice
Consider the following network diagram [insert network diagram from top of p555]. Which of the following statements is TRUE?
A) Activity F can start when Activity D is finished
B) Event 3 is complete when Activity B is complete
C) Activity E must wait for both Activity B and Activity C to finish
D) Activity B can start when half of Activity A is complete
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Consider the event in a network diagram
Q2: What is a precedence table?<br>A) A tabular
Q3: Which of the following statements concerning events
Q4: How might the earliest activity finish time
Q5: Which of the following statements about float
Q7: Which of the following options is the
Q8: Which of the following options is the
Q9: Which statement concerning dummy activities is NOT
Q10: What is the basic process for calculating