Multiple Choice
The is the amount that was budgeted to achieve the work that was scheduled to be performed up to that point in time.
A) total budgeted cost (TBC)
B) cumulative budgeted cost (CBC)
C) cumulative actual cost (CAC)
D) cumulative earned value (CEV)