Multiple Choice
Calculate the cost variance if the cumulative earned value is R10 and the cumulative actual costs are R20.
A) R10
B) -R10
C) 0.5
D) 2.0
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q31: When evaluating work packages that have a
Q33: At the beginning of the project, it
Q34: The is the amount that was budgeted
Q64: When the CPI goes below 1.0 or
Q72: The contractor might try to negotiate payment
Q81: The contractor's outflow of cash can be
Q86: The total project cost is often estimated
Q89: Committed costs need to be treated in
Q95: Cumulative actual cost (CAC)should be calculated to
Q102: Contingency costs in the project costs estimate,