menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Successful Project Management
  4. Exam
    Exam 7: Determining Costs, Budget and Earned Value
  5. Question
    Calculate the Cost Variance If the Cumulative Earned Value Is
Solved

Calculate the Cost Variance If the Cumulative Earned Value Is

Question 29

Question 29

Multiple Choice

Calculate the cost variance if the cumulative earned value is R10 and the cumulative actual costs are R20.


A) R10
B) -R10
C) 0.5
D) 2.0

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q31: When evaluating work packages that have a

Q33: At the beginning of the project, it

Q34: The is the amount that was budgeted

Q64: When the CPI goes below 1.0 or

Q72: The contractor might try to negotiate payment

Q81: The contractor's outflow of cash can be

Q86: The total project cost is often estimated

Q89: Committed costs need to be treated in

Q95: Cumulative actual cost (CAC)should be calculated to

Q102: Contingency costs in the project costs estimate,

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines