Multiple Choice
Committed costs need to be treated in a special way so that the system
A) audits the amounts assigned.
B) periodically assigns a portion of their total cost to actual cost.
C) enters the amount of the cost one time at the end of the project.
D) enters the amount of the cost one time at the beginning of the project.
Correct Answer:

Verified
Correct Answer:
Verified