Multiple Choice
In many cases, especially for smaller projects, most activities involve people resources - that is,
A) all the people who are employed by the project sponsor.
B) all the people who are employed by the project contractor.
C) the members of the project team who may be utilised full time or part time during the project.
D) the stakeholders for the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: Total slack is sometimes called<br>A)drift.<br>B)ride.<br>C)float.<br>D)sink.
Q11: Positive slack indicates the maximum amount of
Q34: The total completion time is 25 days.Task
Q36: One way to determine which activities make
Q52: Once this baseline plan is agreed upon
Q55: As the project progresses, the actual finish
Q56: The sponsor or customer often states the
Q68: Calculate the earliest finish for Task B
Q75: Latest start time (LS)is the latest time
Q94: Negative slack indicates a lack of slack