Multiple Choice
Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
A) day 5
B) day 3
C) day 1
D) Cannot be calculated based upon information given.
Correct Answer:

Verified
Correct Answer:
Verified