A/An _____ Is a Series of Tasks That Requires the Completion

Question 61

Multiple Choice

A/An _____ is a series of tasks that requires the completion of specific objectives within a certain time frame; has defined start and stop dates; consumes resources, particularly time, personnel, and budget; and operates with limited resources.


A) process
B) work order
C) purchase order
D) project
E) team charter

Correct Answer: