Multiple Choice
The loss of support for a project from supporters and observers (who may even join the ranks of those who oppose the project) is an example of risk related to:
A) external suppliers.
B) organisational management.
C) stakeholder relations.
D) timeliness.
E) safety.
Correct Answer:

Verified
Correct Answer:
Verified